Road construction related to national pride projects sees utilization of only 31 percent of capital expenditure as of mid-April

KATHMANDU, May 14: The Department of Roads (DoR), one of the main government entities that work on infrastructure development, spent only 31 percent of the allocated budget to the national pride projects concerned with the construction of roads and bridges in the first nine months of the current fiscal year.
alt=
By Republica

KATHMANDU, May 14: The Department of Roads (DoR), one of the main government entities that work on infrastructure development, spent only 31 percent of the allocated budget to the national pride projects concerned with the construction of roads and bridges in the first nine months of the current fiscal year.



The DoR has received a capital expenditure of Rs 128.27 billion for the fiscal year 2021/22. During mid-July 2021 and mid-April 2022, the department spent only 39.66 billion. The DoR has been constructing 57 projects related to road and bridge construction.


Related story

Progress of road construction under National Pride Project lags...


Meanwhile, the Nagdhunga-Naubise Tunnel Road witnessed work progress of 50.90 percent during the review period. The project has so far constructed 2,796 meters of tunnel out of the total length of 5,499 m.   


 

https://devmyrepublica.nagariknewscdn.com/shared/web/uploads/media/road_20210822130859.jpeg
Related Stories
ECONOMY

Govt makes yet another promise to use development...

Govt makes yet another promise to use development expenditure allocated for next FY
ECONOMY

Postal Highway achieves completion target of 70 pe...

Postal Highway achieves completion target of 70 percent
ECONOMY

Cement production cut down by 70 percent

Cement production cut down by 70 percent
ECONOMY

Public construction works will be carried out in t...

Public construction works will be carried out in two shifts from now onward: Janardan Sharma
ECONOMY

Postal Highway to miss yet another deadline as onl...

Postal Highway to miss yet another deadline as only 65 percent construction completed in over a decade

Trending

Top Videos

Bold Preety willing to fight for her musical career

Awareness among people on heart diseases has improved in Nepal’

Print still remains the numbers of one platform

Bringing home a gold medal is on my bucket

What is Nepal's roadmap to sage child rights